Showing posts with label Crane use. Show all posts
Showing posts with label Crane use. Show all posts

Monday, February 22, 2010

You Tube Video Test

You tube video about crane lift

Monday, January 25, 2010

Monday January 21 2010
8:30 - 9:50 am
Windy with scattered showers (Heavy rains previous evening)

It has been several weeks since the last update to this blog. According to best practices I am not meeting the frequent update quota of 1-2 per week in order to be a successful blogger. That will change. I am going back to the one-a-week or more postings.

Last night we had sever rains and some flood warnings. There appeared to be de-watering taking place in several locations. The main collection area is at the center of the southern area. The eastern part of the site is being prepared for panels while the western part seems to be finishing. The project appears to be divided into four major sections.

This mornings erection of the precast panels was slowed slightly when a JLG lift had to be pulled out of the mud by the crane.

I watch the crane from about 8:30 to 9:45 while it lifted a panal in place and then lifted the JLG out of the mud.

8:36 am: Crane positions for hoist (2 min)
8:38 am: Crane connections are made to panel (2 min)
8:40 am: Liftoff + hover
8:45 am: Panel is walked toward set location and held (approx. half way)
8:53 am: Panel is hoisted to final position
8:54 am: Panel inserted and adjusted
9:32 am: Cables unhooked from panel
9:37 am: Rigging of JLG lift begins
9:41 am: JLG liftoff from mud
9:44 am: JLG lift set

The job seemed to lose about 10 minutes of time by having to relocate the JLG lift. While it may seem minor 4 workers were needed to rig and coordinate the movement. I'd like to think this delay could have been avoided if the lift had been left on the sidewalk in advance of the previous night's storm.




In addition to this delay the crew for the lifts appeared to comprise of:
1 crane operator
2 riggers
1 welder

Posted by PicasaMore to follow...

Thursday, October 1, 2009

Parking Garage 093009

Wednesday
10 am

On Wednesday I watched as a steel rebar cage for the new parking garage structure was lifted and set in place. My assumption was that it would simply be lifted and set within a matter of seconds or minutes. The reality was much more involved. Also the crew members and additional equipment was insightful.



Within the steel rebar cage a constellation-like arrangement of bars was located in the center. This I learned was to give the cage stability when going from a horizontal to a vertical position.

A 1-foot portion of the cage had to be to size before it was lifted. A front-end loader was linked to the cut end and used to move scrap to a nearby pile. The loader was repositioned and a chain was used to attach the bottom of the cage to a hook on the loader bucket.

After readjusting the straps which connect to the crane the lift was underway. The loader was used to assist the crane in getting the cage vertical. Once it was vertical and hovering about one foot off the ground, the loader was unchained. Workers then used a torch to remove half of the interior supports. The cage was then lifted to about midway between its lift and final location. Here two workers take what appear to be rigid foam feet to the bottom of the cage. This must provide the required amount of concrete coverage below the cage.

The cage is lifted in to place and lowered to about half way in to the caisson. At this point the cage is held in place while the remaining interior supports are cut and carefully removed so that no rebar fall in to the caisson excavation. With the supports removed the cage is sufficiently flexible and drops right in to place.




I was so impressed with how my assumptions were trumped by the reality of the operation. Last semester we had performed a rough estimate and schedule for caisson work on the new addition to the building department facility. Our estimate focused on the macro estimating and scheduling tasks, but on observing the actual operation I learned the micro-processes. It was a nice reminder that that is what matters. I need to understand the micro-processes in order to truly understand a job. This job is not simply a caisson drill and crane. It is a crew of 8+, a loader, a rebar cage station, drilling spoilage, caisson excavation safety, a welding torch, etc.

Friday, September 18, 2009

Parking Garage 091709

Wednesday
9am
Overcast

Construction has been underway at the new parking garage structure on campus. Just over a month ago an enclosing fence, runoff screen, and trailers were installed around the site. The site itself consists of an existing parking area. Trees and curbs were removed with excavators and dozers. Starting last week the caisson entourage showed up on site. Caissons will vary in size from two to four feet diameters. A crane and a caisson drill have begun drilling at the north west corner of the site. This photo was taken from the balcony of building across from the site.


The above photo shows the ReBar construction area. Workers use this space to build the caisson cages on site. This seems to be a space and labor intensive way to work. What is the cost/benefit of constructing on site as apposed to off-site and transporting it. It may have to do with paying for transportation twice (material to shop, shop to site).

The video shows the movement of the steel from the assembly to temporary storage area.

In observing the caisson drilling rig I noticed a safety cage which encircled the caisson excavation. This safety cage was roughly waist height and obviously meant to protect workers on the ground from falling in to the pit. Today I observed the drill rigs space needs. The caisson drilled is parallel or in-line with the tract. To the left was a spoil pile where the drill would shake loose soil (which appeared to be a shale of some sort) and to the right were some additional bits which could be swapped out when needed.
Note to self: consider safety enclosure for caisson, spoil area, removal of spoil, extra drill bits. Also there appeared to be a barrel of oil on the drilling rig which seemed to allow easy access to the drill apparatus.

Monday, December 1, 2008

Site Visit 12-01-08

12-01-08
7:58 am (8:20 am Snow)
32 degrees
overcast (muddy soil conditions)


Cold, slight wind, and muddy conditions. To the east, a small lift has gotten stuck in the mud. Also to the east, Stone Masons begin protecting both sides of wall in progress. At the south-west of the site 3 flat-beds have been parked next to a crane and one is making a delivery. All hold a single piece of cast-stone, about 30' long, for the facade. The crane is a an LS-248H (http://www.linkbelt.com/lit/products/ls/248h5/frame_248h5.htm), its not in use. Several workers are waiting for the final delivery to be complete and several drums are offloaded (I assume they contain the anchor bolts).






Click to link to the Site Visit 120108 Web album.


Masons at the north east begin to protect the wall and mortar mixing areas. The wall is protected with plastic, sand is dumped in to a bin and covered, and the workers move off the raising scaffold platform. To the east, masons work to protect the wall in progress with a plastic wrapping on both sides of the wall. Below is a view looking north showing the wall being protected, the steam piping at the east gymnasium wall, and the lift in the lower right hand corner which is stuck in the mud.


Once the snow came, work on the exterior of the building came to a holt. All exterior work more-or-less stopped once it was protected and all interior work proceeded. On the interior of the building pipe fitters continued to install water supply piping, electricians installed junstion boxes at the underside of the gymnasium roof, and carpenters were framing the gymnasium west metal stud wall.

Inside I took the above photo of a mechanical contractars set of plans. (I worked for an architect who used to mark up the documents in the same way to check for errors).

Below is a video of the weather conditions at 8:20 as seen from the second floor.





It had been raining the last couple of days and the perforated corrugated metal decking of the roof made conditions inside wet. With the cold some areas could become somewhat dangerous. Once the snow started I headed down the scaffold from the second floor and noticed the opening for the future window was letting in a snow (which was blowing in from the south) that was landing on the steps of the scaffold. In the future this opening should be covered with plastic to keep the rain and snow off of the scaffold.